Quotation and cost estimate: Plan 3 Open-Plan Contemporary

Quotation no.DateValid untilClient / projectQualityRegion
QT-20261028-0002-P328 Oct 202627 Nov 2026Home buildStandardTier-2 city

Built-up area 528 sq ft over 2 floor(s) on a plot of 442 sq ft (26'-0" x 17'-0").

No.DescriptionUnitQtyRateAmount
A. MAIN BUILDING (CIVIL AND FINISHING)
1Excavation, footing, plinth beam and filling - RCC M25 footings, PCC bed, anti-termite treatmentsq ft528Rs. 214Rs. 1,12,992
2RCC structure: columns, beams and slabs - Fe500D steel, M25 concrete, quality shutteringsq ft528Rs. 468Rs. 2,47,104
3Brick / block masonry - 9 in outer + 4.5 in inner walls, AAC / clay blockssq ft528Rs. 156Rs. 82,368
4Plastering (internal and external) - Cement plaster with sponge / putty finishsq ft528Rs. 117Rs. 61,776
5Flooring, tiling and skirting - Vitrified / porcelain / wooden / anti-skid by roomsq ft528Rs. 214Rs. 1,12,992
6Doors and windows - Teak main door, flush / solid doors, UPVC / aluminium with glasssq ft528Rs. 156Rs. 82,368
7Electrical works - Concealed copper wiring, modular switches, MCB / DB panelsq ft528Rs. 117Rs. 61,776
8Plumbing and sanitary - CPVC / UPVC pipes, branded sanitaryware & CP fittingssq ft528Rs. 117Rs. 61,776
9Painting and finishing - Acrylic putty, primer, emulsion interior + weather-coat exteriorsq ft528Rs. 98Rs. 51,744
10Waterproofing and roof finishing - Terrace, bathroom & wet-area waterproofing systemsq ft528Rs. 58Rs. 30,624
11Staircase and railing - Granite / marble treads, SS / glass / designer railingsq ft528Rs. 58Rs. 30,624
12Kitchen platform, modular units and wardrobes - Granite / quartz platform, modular base units, loft & wardrobessq ft528Rs. 98Rs. 51,744
13Miscellaneous finishing and cleaning - Grills, hardware, false ceiling allowance, final cleaningsq ft528Rs. 78Rs. 41,184
B. SITE WORKS AND EXTERNAL DEVELOPMENT
14Compound wall 5 ft high with plaster and paintrft76Rs. 1,400Rs. 1,06,400
15Main gate and pedestrian gate (MS / designer)lump1Rs. 45,000Rs. 45,000
16Driveway and pavingsq ft30Rs. 140Rs. 4,200
17Garden: lawn, beds, trees, gazebo and irrigationsq ft136Rs. 110Rs. 14,960
18Terrace garden: waterproofing, planters, pergola, grow-bedssq ft102Rs. 320Rs. 32,640
19Underground sump, overhead tank and borewell connectionlump1Rs. 60,000Rs. 60,000
20Rain-water harvesting pit and drainagelump1Rs. 25,000Rs. 25,000

Summary

ItemAmount
A. Main buildingRs. 10,29,072
B. Site works and external developmentRs. 2,88,200
Sub-total (A + B)Rs. 13,17,272
Architect and structural design fee (3%)Rs. 39,518
Approvals, permits and utility connections (1%)Rs. 13,173
Contractor overhead, profit and supervision (8%)Rs. 1,05,382
Contingency (5%)Rs. 65,864
GST at 18% on design and contractor service chargesRs. 26,082
GRAND TOTAL ESTIMATERs. 15,67,291
Cost per sq ft of built-up areaRs. 2,968
Estimated construction time8 months

Amount in words: Fifteen lakh sixty-seven thousand two hundred ninety-one rupees only.

Payment schedule (milestone billing)

StageShareAmount
Advance / booking10%Rs. 1,56,729
Foundation and plinth complete15%Rs. 2,35,094
Columns, beams and slabs complete25%Rs. 3,91,823
Masonry and plastering complete15%Rs. 2,35,094
Flooring, doors and windows complete15%Rs. 2,35,094
Electrical, plumbing and painting complete15%Rs. 2,35,094
Handover and final snag clearance5%Rs. 78,365

Total cost by finish quality (same plan)

QualityTotal estimatePer sq ft
StandardRs. 15,67,291Rs. 2,968
PremiumRs. 21,79,961Rs. 4,129
LuxuryRs. 29,74,414Rs. 5,633

Terms and conditions

Prepared by: Home Planner Client signature: ______________________ Contractor signature: ______________________